On January 9, 2026, Oklo and Meta announced an agreement supporting development of a nuclear-energy campus in Pike County, Ohio capable of scaling to 1.2 GW.
The project is intended to support Meta's growing Ohio data-center operations, including AI infrastructure.
The current planned schedule is:
| Milestone | Target |
|---|---|
| Pre-construction/site work | 2026–2027 |
| General construction | Early 2028 |
| First-phase operation | 2030 |
| Full 1.2 GW buildout | 2034 |
The most important clarification is:
Meta is not currently receiving 1.2 GW from operating Oklo reactors. The agreement supports development of a future phased nuclear campus.
AI workloads require large computing clusters.
Those clusters require:
For hyperscalers, the challenge is not merely buying renewable-energy certificates. They increasingly need new physical power generation that can support long-duration, high-load operations.
Nuclear power can potentially provide:
Advanced-reactor developers argue that smaller units can also be deployed closer to large industrial or computing loads.
Oklo says the agreement provides a mechanism for Meta to:
Oklo plans to use this funding to secure nuclear fuel and advance Phase 1.
This is more economically meaningful than a simple statement that the companies are “exploring nuclear.”
Nuclear projects require substantial capital before revenue begins.
A customer that provides early money can potentially help with:
That may reduce part of the funding burden that would otherwise fall on equity investors.
Oklo's disclosed model remains centered on Oklo developing and operating its own powerhouses.
The agreement is structured around the supply of future power rather than Meta simply purchasing a reactor from Oklo.
1.2 GW equals:
1,200 MW
With current Aurora units designed around 75 MW each, a full-scale campus represents a large multi-unit deployment. Oklo's project materials refer to a 16-unit site when discussing staffing.
Oklo controls more than 200 acres in Pike County at the former Portsmouth Gaseous Diffusion Plant area.
The site also sits near Centrus' Piketon uranium-enrichment operations, creating potential strategic links between:
Oklo and Centrus announced plans to explore a HALEU deconversion joint venture in Pike County.
Then in June, they signed an LOI under which Centrus intends to supply enough HALEU for multiple years of operation for up to five Aurora units, with deliveries scheduled from 2029.
This links:
Fuel production
↓
Aurora
↓
Meta-supported demand
within the same broader Ohio region.
Not yet.
The June announcement explicitly states that the LOI anticipates negotiation of a future definitive agreement.
Therefore, articles should not say:
“Centrus has guaranteed all fuel needed for the entire 1.2 GW campus.”
That would overstate the current commitment.
Oklo currently targets first-phase operations for the Ohio campus as early as 2030.
Between now and then, important steps include:
The project therefore has substantial execution risk despite the size of the commercial opportunity.
The full 1.2 GW campus is targeted for 2034.
That means investors valuing all 1.2 GW as if it were operating today are ignoring nearly a decade of:
The agreement can potentially improve investors' confidence in:
A major hyperscaler wants future nuclear capacity.
Customer prepayments can support development.
The contemplated campus is far larger than a single Aurora unit.
Success could create a blueprint for other data-center customers.
2030 and 2034 are targets, not guarantees.
Large fleets require large quantities of qualified fuel.
Many repeated units must be manufactured and installed.
Commercial regulatory approvals remain necessary.
Oklo must ultimately deliver electricity at economics acceptable to both itself and customers.
No.
It materially strengthens the commercial story, but future revenue still depends on project execution and the detailed commercial arrangements.
Development funding should not automatically be treated as equivalent to decades of realized electricity revenue.
OKLOON is linked to OKLO.
If the market increases its valuation of Oklo because the Meta campus progresses, OKLO may respond and OKLOON may follow.
But OKLOON does not itself represent:
1.2 GW of Meta electricity capacity.
For the product distinction, read What Is OKLOON?.
Up to 1.2 GW.
Pike County, southern Ohio.
As early as 2030 under the current target.
No.
The agreement includes mechanisms for prepayment and early-stage funding.
The Ohio project remains under development. Its capacity, economics, timing, licensing, financing and commercial structure can change.

Key Takeaways Crypto capital gains in Argentina are taxed at a flat 15% rate, while crypto income is taxed at progressive rates of 5%–35%. Holding crypto is not taxed, but selling, trading, or earning

Key Takeaways: Legal Ban: Cryptocurrency operations remain effectively banned without a license under Central Bank regulations. Hidden Tax Risks: While no formal crypto tax exists, sudden fiat profits

Summary OKLOON is an Ondo tokenized product designed to provide economic exposure linked to Oklo Inc. (NYSE: OKLO). MEXC currently provides a dedicated: OKLOON/USDT Spot Market The MEXC market page id

Summary OKLOON is an Ondo tokenized product designed to provide economic exposure linked to Oklo Inc. (NYSE: OKLO). MEXC officially added OKLOON to its Convert service on March 13, 2026 at 10:00 UTC.